PROJECT HISTORY AND ENTITLEMENTS
Completed project entitlements approved
include General Plan and Specific Plan Amendments enabling
599 residential units and a new luxury senior residential
component. Additional approved entitlements include an
approved Master Tract Map 30159; Owners Participation
Agreement (OPA); the designation and adoption of a Redevelopment
Area for the project by the City of Corona; Development
Agreement adoption; a certified Environmental Impact Report
(EIR); Pre-zoning and initial General Plan amendment adoption;
recorded Annexation into the City of Corona; adopted Specific
Plan 99-003: and adoption of a Memorandum of Understanding
(MOU) and Pre-Annexation Agreement.
Resource Agency permitting including Section 7 consultation,
401, 404, and 1603 permits are complete.
The creation of a Community Facilities District (CFD)
was approved for major infrastructure improvements planned
for Temescal Canyon and Weirick Roads.
KEY MILESTONES AND ENTITLEMENTS
City and County Project Approvals
MOU & Pre-Annexation Agreement (Adopted June 7, 2000)
Pre-zoning/Change of Zone (CZ) 98-003 (Adopted June 21,
2000)
General Plan Amendment (GPA) 98-03 (Adopted June 21, 2000)
Environmental Impact Report (EIR) (Adopted June 21, 2000)
Redevelopment Area Established (Adopted July 5, 2000)
Dos Lagos Specific Plan (SP) 99-03 (July 5, 2000)
Development Agreement (Adopted December, 2000)
LAFCO-2000-17-2 Reorganization
Annexation No. 94 (Recorded February 2001)
OPA (Adopted June 6, 2001)
Master Final Tract Map 30159 (Submitted August 1, 2001)
Master Tentative Tract Map 30159 (Approved September 7,
2001)
Public Improvement Construction Plans (Submitted September
17, 2001)
Final Tract Map 30159 (Approved December 19, 2001)
Master Tract Map 30159 (Subsequent Recordation December
28, 2001)
Amendment to the General Plan (GP) 02-005 (Approved June
19, 2002)
Amendment to Specific Plan (SPA) 02-002 (Approved June
19, 2002)
Creation of Community Facilities District (CDF)
(Approved November 6, 2002)
Federal and State Environmental Approvals
U.S. Fish & Wildlife Services Section 7 Consultation
and Biological Opinion
(completed October 2001)
Regional Water Quality Control Board Section 401 Permit
(issued December 2001)
U.S. Army Corps of Engineers Section 404 Permit
(issued February 20, 2002)
Department of Fish & Game 1603 Permit (issued February
20, 2002)